|

|






















|
|
Edgewater Drive
Phase II Design
FAQ
|
 |
1.
|
What
is the Edgewater Drive Design, Phase II Improvement Project?
The Edgewater
Drive Design, Phase II
Improvements will consist of design plan preparation and construction
of
improvements from Harbor Boulevard to Midway Boulevard.
The existing two-lane roadway will be
expanded to four lanes with a grassed median and sidewalks. The existing bridges at Sunrise Waterway,
East Spring Lake Waterway, and West Spring Lake Waterway will be
replaced with new
bridges
with sufficient width for the four lanes, median and sidewalk.
|
2.
|
Why
is this project necessary?
The County’s
goal in providing road improvements is to improve safety and mobility
for the traveling public, while seeking to preserve and enhance the
economic, historic, scenic, and natural qualities of the county roadway
system. As traffic congestion continues to increase in the
immediate area, the overall safety of drivers, bicyclists and
pedestrians will continue to decline. The improvements will
provide new vehicular lanes (for added capacity) along with bicycle and
pedestrian facilities; thus providing a safer corridor for all users.
Edgewater Drive is also a critical corridor providing a hurricane
evacuation route from coastal areas to inland areas. The proposed
improvements will improve mobility for local residents for day-to-day
activities as well as for hurricane evacuations.
|
3.
|
How is the design
and construction
being paid for?
The project
is being paid for utilizing
funds from the local option sales tax or “one-cent sales tax”. This sales tax was first approved by citizens
of Charlotte County in 1994 and was recently extended in 2008 by voter
approval.
|
4.
|
How
much does this project cost?
Preliminary
costs for this project range
from $25 to $27 million with approximately $2.5 million being spent for
engineering design. The construction
cost estimate will be updated at key design milestones as the design
nears
completion. A final construction cost
figure will be determined when bids are requested for construction at
the
completion of the design phase.
|
5.
|
Does
the Charlotte County Board of County Commissioners determine if the
project
will move forward to the design phase?
Yes. The Charlotte County
Board of County Commissioners approved funding for the design phase of
this
project at their October 13, 2009 regularly scheduled board meeting. Construction funding has not been approved at
this time.
|
6.
|
Who
are the Stakeholders in this project?
Community
stakeholders are individuals or organizations/groups with a stake, an
interest, or an investment in a community issue or outcome. Their
interest may stem from a professional or personal interest in an issue
or may result from a commitment to achieve some outcome.
A first step in achieving
meaningful public involvement in project development involves
identifying the individuals and organizations/groups likely to be
affected by the project, those who have a "stake" in its outcome. For
the Edgewater Drive Design, Phase II project, stakeholders will include
owners of property adjacent to the roadway, users of the facility,
Charlotte County Government, transportation service providers in the
area, and a wide range of interest groups. Stakeholders are people
likely to support the project as well as those likely to oppose it. The
views and feedback of stakeholders are important to receive and
consider during a project to ensure a comprehensive solution is
developed.
|
7.
|
What
is Context Sensitive Design Solutions?
Context Sensitive
Solutions is a philosophy that seeks transportation solutions that
improve mobility and safety while complementing and enhancing community
values and objectives. Context Sensitive Solutions are reached through
joint effort involving all stakeholders. Residents, travelers,
communities, businesses, elected officials and many others are all
"stakeholders" in our transportation system.
Stakeholders help
the County and the Design Engineers understand their needs for, and
concerns about, the County transportation system and specifically the
specific characteristics of the Edgewater Drive corridor. The
County can then take this input, along with all of its other work and
analysis, and use it to make planning and design decisions.
The County still
must make the ultimate choices about a project. Safety, the integrity
of the transportation system, and good stewardship of the public's
transportation dollars all remain the County’s responsibilities.
However, thorough stakeholder involvement can contribute to these
decisions and lead to a general consensus about the choices made.
|
8.
|
Is
this project being coordinated with other County projects?
Yes.
Every
effort is being made to
coordinate design and/or construction with other county projects
planned along
Edgewater Drive. In addition to the road
improvements, Charlotte County Utilities will be installing a new water
and
sanitary sewer main along with a irrigation main. These
efforts are being coordinated so all
construction within the project limits is performed at one time thus
reducing
the impact to citizens and creating efficiency in construction (lower
construction costs).
|
9.
|
How can property owners
along Edgewater Drive and
the public learn more?
Property
owners and the public can learn about project progress by regularly
visiting the project's Web site, signing up to receive the project
newsletter by e-mail, and attending community meetings that will be
announced through the local media and on this Web site.
|
10.
|
Will
there be a public meeting for the Edgewater Drive Design, Phase II
Improvement
project?
Yes, three
(3) public meetings are scheduled to be held as part of
the design process. In
addition to the
three (3) public meetings, three (3) presentations will be given before
the
Board of County Commissioners. These six
(6) meetings will provide ample opportunities for public input.
Each public
hearing will have updated plans and comment forms as
well as SED and County staff on hand for questions.
Please refer to the project schedule
for the anticipated dates of the public hearings and presentations
before the
Board of County Commissioners.
|
11.
|
When
will construction begin?
The design
phase is scheduled for conclusion in December of 2010 with
construction anticipated to begin in 2011. While
this date is anticipated please be
advised that funding for construction of the improvements have not been
approved by the Board of County Commissioners.
|
12.
|
Will the County
want to buy an easement or buy my property from me?
The
roadway corridor has an
existing 100’ right-of-way width. This
width, in most cases, will be sufficient to accommodate the roadway
widening. This right of way may be
overgrown or is being used by property owners as part of their private
property.
Property
will most likely be
required to provide room for stormwater management facilities and/or
other
utility structures. In these cases,
vacant properties will be the first choice for placement of these
accessory
uses.
Temporary
easements may be required
during construction to allow for access of equipment and materials
along the
edge of the right-of-way lines. As the
name implies, these easements are for a temporary length of time
(usually the
length of the construction phase) reverting back to the Owner at the
end of
construction.
County
representatives will individually contact every property owner from
which an easement or
property
purchase is needed. This contact usually
occurs after the approval of the 60% submission plan by the Southwest
Florida
Water Management District and County staff.
|
13.
|
Will
environmental permits be obtained
for the project?
As part of
the completion of the 60% design phase, an
Environmental Resource Permit application will be submitted to the
Southwest
Florida Water Management District, Florida Department of Environmental Protection (DEP), and the United States Coast Guard. Please
refer to the project schedule for the
anticipated date of this submittal.
|
14.
|
How
will the project affect wetlands and other natural resources?
The project
area includes wetlands throughout the length of the
corridor. The project will be designed
to avoid wetlands where possible, and to minimize and mitigate wetland
impacts
where avoidance is not possible. A
jurisdictional
wetland survey will be prepared at the onset of the design phase so
critical
areas can be accounted for while looking at alignment alternatives.
|
15.
|
I
see people working along Edgewater Drive and the surrounding
properties. Who
are they and what are they doing?
As part of
preparing construction plans for the project, SED staff
and consultants have been performing field surveys, data collection,
geotechnical borings, and similar required functions. The design
consultants
working for SED carry a letter stating their purpose along with
contacts for
further information.
Please note that F.S. Statues
471.027 and 472.029 gives authorization for engineers, surveyors
and
mappers to enter lands of third parties without permission but must not
damage
physical items on or within the property.
|
16.
|
What are
Roundabouts and why are they being considered?
A roundabout is one of several types of
circular road junctions or intersections at which traffic is slowed
down and enters a one-way stream around a central island. When
completely rebuilding an entire roadway it is prudent to investigate
all options that may (or may not) be of benefit to the driving
public. One such option is the use of Roundabouts in lieu of the
traditional signalized or stop controlled intersection. Several
advantages of using roundabouts are as follows:
Roundabouts are
safer than signal controlled junctions, with accidents usually
occurring at a slower speed and at a slight angle instead of
right-angle or rear end collisions at junctions.
Roundabouts
allow for easy u-turns, including for larger vehicles, which are
sometimes impossible or forbidden in normal road junctions.
Roundabouts
(and other circular intersection types) allow for landscaping,
monuments, and other aesthetic uses within the central island.
Most roundabouts are not controlled by
traffic lights. This has several advantages:
Reduced
waiting time for drivers, less fuel wasted while idling and thus better
air quality.
Reduced
operating costs for lamp replacement and electricity.
Drivers can
focus on the street level for other cars and pedestrians.
Roundabouts
still function as designed during electrical power outages.
Roundabouts also have some disadvantages
when using in lieu of signalized or stop control intersections:
Roundabouts
require all traffic to slow down, and thus may be undesirable where a
high-volume road would otherwise not be required to stop.
A roundabout
occupies more space than crossroads at the intersection point. However,
traffic signals often require construction of turn lanes for capacity
and safety, and therefore traffic signals may occupy more space overall
than a roundabout at the same location.
Drivers may
become confused and use roundabouts improperly, especially in areas
where roundabouts are uncommon, or where traffic circles or rotaries
also exist.
The central
island of a roundabout can be a hindrance to movement of oversize
vehicles. Highway designers can design for oversized loads, if they are
aware that they will be using the route.
Obstruction
to departing vehicles can result in blockage of all approaches to the
roundabout until the obstruction clears. When exiting vehicles queue
into the roundabout, they obstruct both entering and circulating
traffic. In a non-roundabout intersection, particularly those with
exclusive turn lanes, traffic flow can typically be maintained in
directions parallel to the uctionobstr.
|
|
|
|